Weld Square Primary School - New Administration Building

Project Name: Weld Square Primary School - New Administration Building

Client: Building Management and Works

Architect: Zuideveld Marchant Hur

Project Value: $1,149,647

Project Description:

The New Administration Building at Weld Square Primary School comprised of the construction of a new reception/foyer, three new office spaces, interview room, medical room, UAT, Duplicating room, Comms room, cleaners store,  secure store and landscape works.

The works included:

  • Demolition of existing brick wall, retaining wall, concrete footings, paving and kerbs.
  • Clearing of existing vegetation and levelling of the site.
  • Installation of new concrete footings, slab and pathways around the Administration building.
  • Fabrication and erection of structural steel framework.
  • Construction of double brick masonry walls.
  • Installation of roof safety mesh, insulation, Colorbond sheeting, downpipes, gutters, associated flashings and three solar tubes.
  • Installation of cladding and external screens.
  • Electrical works consisted of installation of a new electrical wiring, new intruder detection system, data points, powerpoints and lighting. Relocation and extension of the existing school PA/Siren systems and assistance call systems to the new administration.
  • Hydraulic works consisted of stormwater/sewer pipework, drainage, water supply and hydraulic fitoff.
  • Mechanical works included installation of new ducted split air conditioning system and exhaust fan system to UAT and medical room.
  • Installation of new aluminium doors and windows.
  • Fabrication and installation of new cabinetry in medical room, duplicating room and reception/foyer area.
  • Installation of new carpet and vinyl.
  • Installation of tiles and fit out of UAT.
  • Installation of new signage.
  • Carpark works consisted of installation and compaction of new limestone subbase and roadbase. Installation of concrete kerbs, primer and asphalt.
  • External/Landscaping works consisted of reticulation, soil preparation, mulch, grass, paving, gates.